Engineering, Procurement and Construction of Gas Compressor Unit of South Pars Gas Field Phase 15 &16
The South Pars Gas Field Development Phase 15 &16 will be developed to produce 2 BSCFD reservoir fluids which will be reached in onshore facilities. Onshore processing facilities consist of condensate stabilization, NGL fractionation, gas treatment, propane and butane treatment, MEG regeneration, Sulfur recovery, export unit, etc. Export unit (Unit 106) is aimed to increase discharge pressure of treated lean Gas & boost it into gas trunk line for domestic and export purposes. In its 5+2 arrangement, each compression train includes one Centrifugal compressor and gas turbine driver, one suction drum, one after cooler and other required facilities.
POGC
2008
2
108
Abadan Refinery Upgrading Project (EPC)
Engineering, Procurement and Construction of 11 Tanks of Abadan Refinery
Dismantling of 13 nos. of existing storage tanks, construction of eleven floating and fixed roof storage tanks with total capacity of 210,000 m3 and related facilities was including electrical substations, control system, tank gauging system, F&G system, fire fighting system, fuel pumps, utilities etc.
NIOEC
2007
3
107
Birjand Oil Tank Farm (EPC)
Engineering, Procurement and Construction of Birjand Oil Tank Farm
Birjand Oil Tank Farm is comprised of thirteen tanks with total capacity of 700.000 bbl for storage of gasoline and gas oil. APG is responsible for engineering, supply of materials & equipment , civil works and construction of the tank farm and related facilities including loading/unloading arms, fuel transfer pump units, tank gauging system, F&G and fire fighting system, electrical substation ,etc.
NIOPDC
2006
4
106
Four Gas Compressor Stations of Azerbaijan 48'' Pipeline (P)
Procurement Services & Supply of Piping, Mechanical & Machinery, Electrical, Control & Instrumentation Materials & Equipments
Natural gas received from the IGATs is boosted through Azerbaijan Pipeline to north and north west of the country for domestic consumption and export purposes. Qazvin, Khoramdarreh, Nikpei and Hashtrood Stations are aimed to enhance the capacity of the line from 60 MMSCMD to 110 MMSCMD. APG as a procurement contractor has supplied all piping, mechanical, electrical, control and instrumentation equipment and materials needed for execution of the stations. The overall process of the job including procurement engineering, PO placing, shipment, custom clearance and delivery of the goods at client's sites were all done within 10 months.
NIGC
2005
5
105
Four Gas Compressor Stations of IGAT IV (MC)
Management Consultant
APG as management consultant of this project involved in endorsement or basic design, review and verification of detail design and supervision on construction, commissioning and start-up of stations no. 5,6,7 & 8 of IGAT IV which are named Arsanjan, Safashahr, Abadeh and Shahreza respectively.
NIGC
2005
6
104
Nikpey Gas Compressor Station Of Azerbaijan 48" Pipeline (C)
Construction, Commissioning & Start-up
Civil works, installation, pre- commissioning, commissioning and start-up of the Station
NIGC
2005
7
103
Qazvin Gas Compressor Station of Azerbaijan 48" Pipeline (C)
Construction, Commissioning & Start-up
Civil works, installation, pre- commissioning, commissioning and start-up of the Station
NIGC
2005
8
102
Khoramdarreh Gas Compressor Station of Azerbaijan 48" Pipeline (C)
Construction, Commissioning & Start-up
Civil works, installation, pre- commissioning, Commissioning and start-up
NIGC
2005
9
101
Shanoul Manifold (EPC)
Procurement of Material & Equipments, Construction, Commissioning & Start-up
Shanoul Manifold is aimed to gather natural gas from ten wells and transfers it to Persian refinery via 24" pipeline. APG has done engineering and design. procurement of all piping, fixed and rotary equipment, electrical, control and Instrumentation materials, civil works and construction of Shanoul Manifold within 17 months